Streetscape All Phases

Phase A – Mill Street

Location: Almonte Street to Brae Street

Estimated Date: Completed

Items to Complete: Underground servicing, road construction, concrete work, pedestrian crosswalks, base road asphalt and rough landscaping.

Phase B – Mill Street

Location: Brae Street to Little Bridge Street

Estimated Date: Completed

Items to Complete: Underground servicing, road construction, concrete work, base road asphalt and rough landscaping.

Phase C – Brae Street

Location: High Street to Mill Street

Estimated Date: February 27th, 2023 - May 1st, 2023

Items to complete: Underground servicing, road construction, concrete work, base road asphalt and rough landscaping.

Phase D – High Street Parking lot

Location: Brae Street to Bridge Street

Estimated Date: April 4th, 2023 - May 1st, 2023

Items to Complete: Road / parking lot construction, concrete work, base road / parking lot asphalt and rough landscaping.

Phase E – Little Bridge Street

Location: Bridge Street to Mill Street

Estimated Date: March 6th, 2023 - June 20th, 2023

Items to Complete: Underground servicing, road construction, base road asphalt, concrete bridge wall repairs, and rough landscaping.

Phase F – Mill Street

Location: Little Bridge Street to Bridge Street

Estimated Date: June 14th, 2023 - July 21st, 2023

Items to Complete: Road construction, concrete work, road asphalt and rough landscaping.

Final Phase (Entire Site)

Estimated Date: July 24th, 2023 - July 28th, 2023

Items to Complete: Final landscaping, final paving and pavement markings.