Streetscape All Phases

Phase A – Mill Street

Location: Almonte Street to Brae Street

Estimated Date: April 19th 2022 – August 11th 2022

Items to Complete: Underground servicing, road construction, concrete work, pedestrian crosswalks, base road asphalt and rough landscaping.

Phase B – Mill Street

Location: Brae Street to Little Bridge Street

Estimated Date: August 12th 2022 – September 16th 2022

Items to Complete: Underground servicing, road construction, concrete work, base road asphalt and rough landscaping.

Phase C – Brae Street

Location: High Street to Mill Street

Estimated Date: September 9th 2022 – October 24th 2022

Items to complete: Underground servicing, road construction, concrete work, base road asphalt and rough landscaping.

Phase D – High Street Parking lot

Location: Brae Street to Bridge Street

Estimated Date: October 24th 2022 – November 14th 2022

Items to Complete: Road / parking lot construction, concrete work, base road / parking lot asphalt and rough landscaping.

Phase E – Little Bridge Street

Location: Bridge Street to Mill Street

Estimated Date: November 14th 2022 – December 16th 2022

Items to Complete: Underground servicing, road construction, base road asphalt and rough landscaping.

Phase E – Little Bridge Street

Location: Bridge Street to Mill Street

Estimated Date: April 20th 2023 – May 18th 2023

Items to Complete: Completion of concrete works, bridge wall repairs and landscaping.

Phase F – Mill Street

Location: Little Bridge Street to Bridge Street

Estimated Date: May 18th 2023 – June 23rd 2023

Items to Complete: Road construction, concrete work, road asphalt and rough landscaping.

Final Phase (Entire Site)

Estimated Date: June 23rd 2023 – July 23rd 2023

Items to Complete: Final landscaping, final paving and pavement markings.