Downtown Almonte Revitalization Schedule
Phase A – Mill Street
Location: Almonte Street to Brae Street
Estimated Date: April 19th 2022 – August 11th 2022
Items to Complete: Underground servicing, road construction, concrete work, pedestrian crosswalks, base road asphalt and rough landscaping.
Phase B – Mill Street
Location: Brae Street to Little Bridge Street
Estimated Date: August 12th 2022 – September 16th 2022
Items to Complete: Underground servicing, road construction, concrete work, base road asphalt and rough landscaping.
Phase C – Brae Street
Location: High Street to Mill Street
Estimated Date: September 9th 2022 – October 24th 2022
Items to complete: Underground servicing, road construction, concrete work, base road asphalt and rough landscaping.
Phase D – High Street Parking lot
Location: Brae Street to Bridge Street
Estimated Date: October 24th 2022 – November 14th 2022
Items to Complete: Road / parking lot construction, concrete work, base road / parking lot asphalt and rough landscaping.
Phase E – Little Bridge Street
Location: Bridge Street to Mill Street
Estimated Date: November 14th 2022 – December 16th 2022
Items to Complete: Underground servicing, road construction, base road asphalt and rough landscaping.
Phase E – Little Bridge Street
Location: Bridge Street to Mill Street
Estimated Date: April 20th 2023 – May 18th 2023
Items to Complete: Completion of concrete works, bridge wall repairs and landscaping.
Phase F – Mill Street
Location: Little Bridge Street to Bridge Street
Estimated Date: May 18th 2023 – June 23rd 2023
Items to Complete: Road construction, concrete work, road asphalt and rough landscaping.
Final Phase (Entire Site)
Estimated Date: June 23rd 2023 – July 23rd 2023