Downtown Almonte Revitalization Schedule
Phase A – Mill Street
Location: Almonte Street to Brae Street
Estimated Date: Completed
Items to Complete: Underground servicing, road construction, concrete work, pedestrian crosswalks, base road asphalt and rough landscaping.
Phase B – Mill Street
Location: Brae Street to Little Bridge Street
Estimated Date: Completed
Items to Complete: Underground servicing, road construction, concrete work, base road asphalt and rough landscaping.
Phase C – Brae Street
Location: High Street to Mill Street
Estimated Date: February 27th, 2023 - May 1st, 2023
Items to complete: Underground servicing, road construction, concrete work, base road asphalt and rough landscaping.
Phase D – High Street Parking lot
Location: Brae Street to Bridge Street
Estimated Date: April 4th, 2023 - May 1st, 2023
Items to Complete: Road / parking lot construction, concrete work, base road / parking lot asphalt and rough landscaping.
Phase E – Little Bridge Street
Location: Bridge Street to Mill Street
Estimated Date: March 6th, 2023 - June 20th, 2023
Items to Complete: Underground servicing, road construction, base road asphalt, concrete bridge wall repairs, and rough landscaping.
Phase F – Mill Street
Location: Little Bridge Street to Bridge Street
Estimated Date: June 14th, 2023 - July 21st, 2023
Items to Complete: Road construction, concrete work, road asphalt and rough landscaping.
Final Phase (Entire Site)
Estimated Date: July 24th, 2023 - July 28th, 2023
Items to Complete: Final landscaping, final paving and pavement markings.