Municipality’s 2025 Surface Treatment Program Starts this Week
The Municipality of Mississippi Mills will begin works approved as part of the 2025 surface treatment program this week.
The following roads will receive grading and surface treatment:
- Concession 8 North, Pakenham (intersection of Mountain View Road and Barrie Road to Waba Road) – to start on or around July 7
- Rae Road (Ramsay Concession 8 to County Road 29) – to start on or around July 9
- Dark’s Side Road (Kinburn Side Road to municipal limits) – to start on or around July 14
Arnott Brothers Construction is taking on these works and will make efforts to minimize disruptions during construction.
Any concerns should be directed to:
Rob Crain
President, Arnott Brothers Construction
info@arnottbros.com
613-812-0575
Robert Smith
Mississippi Mills Roads and Public Works Technologist
smithr@mississippimills.ca
613-256-2064
All residents in the affected areas have received notification.
These projects are part of the original surface treatment program works approved by Council in the 2025 Budget. Additional works approved by Council in June will be added to the schedule.
Watch for construction signage and detour information. Slow down around crews.
Further updates to come on additional projects.
Surface treatment projects are expected to finish by the end of August.
Contact Us
MUNICIPAL OFFICE
3131 Old Perth Rd
Box 400
Almonte ON, K0A 1A0
Email: Town@mississippimills.ca
Phone: 613-256-2064
HOURS OF OPERATION
Monday to Friday, 8:30 a.m. to 4:30 p.m. except on Statutory Holidays
Sign up to our newsfeed
Stay up to date on the municipality's activities, events, programs and operations by subscribing to our daily news digest