Surface Treatment Program Update – July 29, 2025

The Municipality’s surface treatment program continues to progress well and ahead of schedule.
Project updates:
- 8th Concession North Pakenham (Waba Road to Barrie Road) – works completed
- 12th Concession South Pakenham (Darks Side Road to Kinburn Side Road) – works completed
- Darks Side Road (Kinburn Side Road to municipal limits) – works completed
- Rae Road (County Road 29 to 8th Concession Ramsay) – to be completed week of August 11
- Rae Road (4th Concession Ramsay to 5th Concession Ramsay) – to be completed week of August 11
Additional projects:
- Water Street (Bridge Street to end of road)
- Townline Road West (Highway 7 to municipal limits)
- Pick Road (County Road 29 to 8th Concession Ramsay)
Watch for construction signage and detour information in these areas. Please slow down for crews.
The 2025 surface treatment program is expected to be completed by August. Watch for further updates.