DOWNTOWN ALMONTE CONSTRUCTION 2023

Construction Update 

Construction within Phase C – Brae Street

Cavanagh Construction is currently working within Phase C – Brae Street of the downtown core reconstruction project.  Efforts are focused on the installation of new watermain, storm sewer and sanitary sewer systems.  The installation of underground work is approximately 70% complete and scheduled to be completed next week.

 

 

 

Traffic Phase C – Brae Street

A full road closure has been in effect since March 2nd, 2023, beginning at Almonte Street, and progressing up Mill Street towards Brae Street.  Accessibility to businesses that require deliveries and or access will be accommodated.  As construction progresses, access from Almonte Street will be restored. 

 

 

 

Commencement of construction within Phase E – Little Bridge Street

Cavanagh Construction is set to recommence Phase E – Little Bridge Street construction activities as part of the Downtown Revitalization project on April 3rd, 2023.  The work includes cutting and removing sidewalks/asphalt, tree removal, and installation of temporary signage.  Installation of temporary watermain, and sanitary sewer bypasses will start once removal works have completed.  Prior to any planned water disruptions, affected residents and businesses will receive hand-delivered notices. 

Traffic Phase E – Little Bridge Street

A road closure will be in effect beginning April 3rd, 2023, between Mill Street and the entrance to Thoburn Mills.  Accessibility to businesses that require deliveries and or access will be accommodated.  As construction progresses, access from Mill Street will be restored.  

Please note that garbage collection shall remain the same and bins will be relocated for collection and back to residence/businesses by end of day. 

Cavanagh Construction Contact Info

Cavanagh Construction has delivered their notification to residents and businesses; they can be contacted at the following:

 

Hilary Lalonde
Project Manager
Thomas Cavanagh Construction Ltd.
Cell: 613 298 8524
Email: HLalonde@thomascavanagh.ca 

ALTERNATE AFTER HOURS

Tim Rainville
Sewer & Water Superintendent
Thomas Cavanagh Construction Ltd.
Cell: 613 282 5018

Randy Kubusheskie
Roads Superintendent
Thomas Cavanagh Construction Ltd.
Cell: 613 913 9252

 

For More Information

We request that property owners and businesses provide contact information to ensure you receive any future notifications.  Emails can be sent directly to the project manager listed below.  Should you have any questions, comments or concerns related to the project or require special accessibility accommodations, please let us know by contacting the project manager noted below.  Your communication is critical to ensure this project is a successful one. 

The Municipality of Mississippi Mills would like to thank you for your patience and co-operation during this construction project.  For more information, please visit our website at: https://www.mississippimills.ca/en/build-and-invest/downtown-almonte-revitalization.aspx 

 

Municipal Contacts:

Robert Smith
Project Manager
Roads & Public Works Technologist
Mississippi Mills
613 256 2064 x404
smithr@mississippimills.ca

Cory Smith
Director of Roads & Public Works
Mississippi Mills
613 256 2064 x401
csmith@mississippimills.ca